Fertilizer production facility with on-site energy generation on a rural Ozark site
Project Summary
A $244,098,940 production facility on a rural Arkansas site, of which $208,479,813 is program-allowable under the grant's fertilizer-scope screen. The study separated the two questions the agency actually has to answer — whether the fertilizer scope stands on its own, and whether the wider facility can be executed — and answered them independently.
What the Project Included
Fertilizer production capacity with supporting on-site energy generation, together with the receiving, process, storage, and outbound logistics infrastructure the site requires.
Capital Structure
$244,098,940 total project cost, of which $208,479,813 is program-allowable under the fertilizer-scope screen; the balance sits outside program scope and is carried by the sponsor.
Feasibility Study Challenges
The study priced execution risk explicitly rather than treating the facility as routine. Coverage was reported three ways to keep the record honest: 1.52× fixed-charge coverage against obligations that actually exist, an illustrative 2.52× against a note that does not yet, and roughly nine times coverage of the one recurring maintenance reserve. The favorable determination is conditioned on execution gates — scope conformance, phased commissioning, and entity conformance — not assumed away.