IndependenceFor lender-commissioned feasibility studies, fiduciary duty runs to the lender and agency — not to the borrower. Other assignments follow their signed engagement scope. Determinations are independent and never revised under commercial pressure.  ·  International assignments accepted case by case.
Approved project summary

Restoration of an idle sugar refinery to production — approximately 359,000 SF of processing, warehouse, and cane-yard facilities

Location: Santa Rosa, Texas, USALocation status: Coarse location; map pin available.Project type: Agricultural ProcessingPrograms: USDA B&I · 7 CFR Part 5001

Project Summary

Restoration of an idle sugar refinery in Santa Rosa, Texas to full production through infrastructure rehabilitation, modernization, and recommissioning. The property includes approximately 359,000 square feet of industrial buildings, warehouses, processing facilities, and cane yards together with supporting utility infrastructure. At design capacity the facility processes approximately 2.05 million tons of cane annually, equivalent to roughly 246,000 tons of refined sugar.

Market Position

The refinery’s Rio Grande Valley location provides dual-market access: the Texas market, which consumes more than 500,000 tons of refined sugar annually, and the established refining corridor served by Louisiana and Florida producers located far from the border. This dual access materially enhances revenue stability relative to a single-market processor and underpinned the demand analysis.

Capital Structure

Total capitalization of $38,110,000, funded by $25,000,000 of USDA Business & Industry guaranteed debt and $13,110,000 of equity provided by aligned sponsors. The structure places roughly one-third of the capitalization in equity ahead of the guaranteed facility, consistent with the tangible-balance-sheet expectations of 7 CFR Part 5001.

Feasibility Study Challenges

Restoring a dormant heavy-processing asset concentrates risk in the technical dimension: rehabilitation scope, commissioning schedule, and cane supply contracting all had to be evidenced rather than assumed. The analysis therefore weighted contractor capability, equipment condition, and grower-supply arrangements alongside the financial projections, and stated each dependency plainly as a condition of the program rather than absorbing it into base-case assumptions.

Legal disclosure. Wert-Berater, Inc. offices are mailing addresses only. Following the COVID-19 pandemic the firm has elected to work remotely; its office locations receive mail and are not staffed for visitors or in-person meetings. Headquarters mailing address: 1968 South Coast Hwy, Ste 2382, Laguna Beach, CA 92651.

Wert-Berater, Inc. is an independent provider of feasibility studies and other related services. The firm does not provide financing or equity investment advice, and does not arrange, broker, or place debt or equity capital of any kind.

All appraisal assignments are performed by Bruce E. Jones, MAI, ASA-GC, BCA, CMEA, a member of the Appraisal Institute since 2006, a staff member of Wert-Berater, Inc. and owner of Special Purpose Realty Valuation.

Services  ·  Experience

© 1998–2026 Wert-Berater, Inc. All rights reserved.